Construction - 6x8 Hut - Hut Deploy Checklist
Panels:
-
Floor
- Floor insulation
- Floor cover
- Floor rail studs
-
4 cinder blocks
- Shims
- Rear wall
- Side wall 1
- Side wall 2
-
Front wall
- Door
- Hinges w/correct screws
- Lock
- Chain
- Transom plastic
- Kickstop studs
-
Loft
- Supports
- Ladder support
- Ladder rungs
- Gables
- Topper
-
Roof panel
- 2 side overhangs, 7' long by 6+" wide
- 1 front overhang, 8' long x ~ 12" wide
- 1 96" 2x4 or 2x6 'lock stud'
- 1 roll roofing
Stove:
-
Stove
- Bricks
- Bolts
- Grate
- Stove shield
- Stovepipe
- Flashing
Tools:
Hand tools
-
Hammers
- 16d nails
- 8d nails
- Roofing nails
- Pry bar
- Cats paw
-
Staple gun
- Staples
- Shears/snips
Power tools
-
Drills or impact drivers
- Driver bits
- 1"-1.25" spade bit
- 3" screws (plenty)
- 1.5" screws
-
Sawzall
- Saw blades
- Spare batteries
Measuring and marking
- Measuring tapes
- Chalk line
- Markers
- Level
Painting:
- 2 gallons paint
- Rollers
- Roller covers
- Paint pans
Ground prep:
- Shovels
- Rakes
- Machete
Safety:
- First aid kit
- Fire Extinguisher
- Gloves
- Goggles
- Sunscreen
- Beverages
- Bug spray
Transport and setup:
- Straps
- Pickup
- Tarp
- Trash bags
Etc:
- Ladders
- Nail aprons
- Heavy-Duty strap
- Crack foam/caulk + gun
- Client flyers
- Notebook
- Camera